PISMO BEACH, Calif. — The first major structure of the Five Cities Project is now standing. Crews have finished the concrete work on a 1,200-foot retaining wall along Price Street and U.S. 101, the San Luis Obispo Council of Governments (SLOCOG) announced, and the work is shifting to the next stage.
What Just Got Finished
Crews broke ground on the wall on April 6, so the concrete work took a little over seven months.
The wall has a specific purpose. Engineers needed it so that a third lane can fit on Highway 101 while leaving alone a culturally sensitive rock formation in the median. Planning documents identify that formation as Pismo Rock, an important Chumash cultural site.
What Happens Next
- At the wall: Backfilling around it and drainage upgrades nearby are the next jobs at that site.
- At the bridges: work continues at the Spyglass and Mattie Road bridges.
- On the ground: Caltrans crews will prepare the ground for new roadway and install more drainage systems.
- Underground: work on buried infrastructure is about to begin.
What It Means for Drivers
Pismo Beach and all of its businesses stay open and reachable throughout. Officials are asking drivers to allow extra time and follow the traffic control signs, because delays are expected.
Earlier warnings from SLOCOG named the likely slow spots: Price Street between downtown and Mattie Road, and the undercrossings at Spyglass Drive, Mattie Road and Wadsworth Avenue.
With Thanksgiving traffic arriving next week, anyone driving through Pismo Beach should plan for a slower trip than usual.
What the Whole Project Will Build
The full name is the Five Cities Multimodal Transportation Network Enhancement Project. It is a joint effort by SLOCOG, Caltrans and the City of Pismo Beach. KSBY has described it as an $85 million package with three parts:
| Part | What it is |
|---|---|
| Part-time travel lane | A third southbound lane on about five miles of Highway 101, between Avila Beach Drive and Price Canyon Road |
| Park-and-ride lot | A commuter lot in Pismo Beach, with electric vehicle chargers planned |
| Shared-use path | A walking and cycling path along Shell Beach Road |
How the Part-Time Lane Will Work
This is the unusual part of the project. The new lane is not a regular full-time lane.
- Hours: Drivers would get the extra lane only during the afternoon rush, from 2 p.m. to 7 p.m. each day.
- Signals: Overhead signals will tell drivers when the lane is open.
- A trial run: The lane counts as a pilot for its first seven years, after which Caltrans would seek legislative approval to keep it.
- Rare in California: when it was planned, only one other highway in the state had a part-time lane on its inside shoulder.
The goal is to relieve the southbound backup that builds through Shell Beach and Pismo Beach on weekday afternoons and busy weekends.
The Timeline
Planning goes back to 2014. Highway construction began this year, and SLOCOG’s timeline has it lasting through 2028.
SLOCOG posts regular construction updates on its Five Cities Project page.
Joel J. Wallace is a writer and editor at smhsbreeze.com, where he covers local news and crime stories. He focuses on clear, accurate, and timely reporting that keeps readers informed about the events and issues shaping their community today.